Macksville CBD Road Works

Macksville CBD Update - Tuesday 26 September 2.00pm

The new pedestrian crossing and median refuge concrete works will be completed this afternoon.

  • Wednesday 27 September – Final asphalt wearing course for Wallace Street. Road closed from 12.00pm (midday) to 2am on Thursday 28 September, detours in place.
  • Friday 29 September from 4.00am to 9.00am – Line marking and reflective pavement markers. Road closed, detours in place.

 



Macksville CBD Works – Upcoming Road Closure

Wallace Street will be closed between Cooper Street and the Princess Street intersection from 12.00pm Wednesday 27 September for asphalt preparation and surfacing. The final asphalt wearing course is scheduled for 6.00pm.

Macksville CBD 25092023.png

Macksville CBD Update Thursday 21 September 11.00am

  • Last week - Final asphalt laying and line marking completed in Princess, McKay and River Streets
  • This week – works to the new Wallace Street pedestrian crossing and median refuge commenced
  • The new pedestrian crossing and medians are scheduled to be completed before Wednesday 27/9 weather pending
  • Wednesday 27/9 – Night works – final asphalt wearing course scheduled
  • Friday 29/9 – 5am to 9am – line marking scheduled

20230920 - Pedestrian Crossing - Wallace Street - (9).JPG

 

Macksville CBD Update Monday 11 September 2.30pm

7am to 6pm – Section F2 – River Street – Road closure in place – commence profiling works.
2pm to 4pm – Section G – River Street – Road closure in place – commence profiling works.
4pm to 4am – Section A – McKay to Princess to Wallace Streets – road closure in place – install final wearing course asphalt laying.

 

 

Macksville CBD Update Friday 8 September 12.30pm

Monday 11 September

7am to 6pm – Section F2 – River Street – Road closure in place – commence profiling works.

6pm to 4am – Section A – McKay to Princess to Wallace Streets – road closure in place – install final wearing course asphalt laying.

 

Tuesday 12 September

7am to 6pm – Section G – River Street – road closure in place – commence profiling works.

8am – Section A – reopen to through traffic.

1pm to 3pm – Sections F1, F2 & G – River Street and part of Princess Street – full road closure – apply bitumen water proofing seal.

6pm to 4am – Sections F1, F2 & G – River Street and part of Princess Street – full road closure – install final wearing course asphalt laying.

 

Wednesday 13 September

8am – Section’s F1, F2 & G – reopen to through traffic.

 

Thursday 14 & Friday 15 September

Final line marking under traffic control.

 

CBD Map.png

 

 

 

Macksville CBD Update 7 September 2.00pm

Wallace Lane Delivery Disruption – Wallace Lane will be closed tomorrow (Friday 8 September) at the River Street end for trench stabilisation works. Alternate access for deliveries to Wallace Lane will be via Wallace Street. Traffic Controllers will assist delivery drivers to reverse into Wallace Street safely when leaving.

 

 

Macksville CBD update Monday 4 September 4.00pm

  1. Section C and D – asphalt works have been completed and the road will reopen tomorrow morning.
  2. Section F and G – River Street will be closed to traffic with works on Thursday 7 and Friday 8 September from 7am. The road will be open to traffic after hours.
  3. Delivery vehicles to Wallace Lane will experience minor delays. Deliveries to businesses fronting River St will be difficult to accommodate, please contact Matt Leibrandt on 0409829724 for further information.
  4. Kerbside Waste Collections - River Street premises will be affected during the construction. Please ensure bins are placed out of the work zone area.

 

 

Macksville CBD Update Wednesday 30 August 12.30pm

  • Section C concrete is scheduled to be poured tomorrow morning – Thursday 31 August.
  • Asphalt is scheduled for Monday 4 September and the heavy vehicle route is scheduled for reopening on Tuesday 5 September.
  • Kerbside Waste Collection will remain unchanged from last week. Please ensure rubbish bins are placed out of the work zone area.

CBD - 30 Aug.png

 

Macksville CBD Update Wednesday 23 August 12.30pm

  • Asbestos water main and stormwater pipe works commencing today (23/8) in Section F with works to continue into Section C
  • Section D concrete to be poured on Thursday (24/8)
  • Section E to be excavated on Friday (25/8)
  • Section D & E to be asphalted on Monday (28/8)
  • Section C excavations to commence Tuesday (29/8)

 

Kerbside Waste Collections – Thursday 24 August

Waste collections will be affected tomorrow morning. Bins normally placed in Sections B, C & D will need to be placed out of the work zone area. No access will be available to the Princess/McKay Street intersection.

Sections C & D:  The kerbside collection truck route will be via the McKay/River Street carpark – see below image.
Section B: waste collections will be picked up from either McKay Street across from the carpark or on the corner of Wallace/Princess Street intersection.

CBD-24-Aug.png

08082023_update.png

 

Macksville CBD Update - Monday 21 August 8.30am


Please be advised that the scheduled asphalt works for Monday 21 August has been delayed by one day. This work will now occur Tuesday 22 August. As a consequence the northern lane on Wallace Street will be re-opened to through traffic Wednesday 23 August. Council apologises for this unscheduled delay.


Macksville CBD Update - Thursday 17 August 3.30pm

  • The concreting in Section B was successfully completed today, with asphalting to occur on Monday.
  • The excavation in Section D will commence on Monday.
  • Wallace Street to return to two-way traffic on Tuesday.

 

Macksville CBD Update – Tuesday 15 August 4.30pm

As Council’s concrete crew and roadworks contractors continue to work on Section B (Princess Street between Wallace and McKay Street), residents/business owners are advised that weekly rubbish collections will be affected.

Bins normally placed in this section of road will be required to be moved to Wallace Street or McKay Street out of the work zone area. Bins placed in Wallace Street between Princess Street and Matilda Street will be collected.

 

Macksville CBD Update Monday 14 August 10.30am

  • Road pavement works to Princess Street between Wallace and McKay Streets have commenced this morning.
  • The asphalt laying works are currently underway over the new concrete at the intersection.
  • Once the asphalt works have been completed this afternoon the east bound traffic flow of Wallace Street will be opened.
  • On Tuesday 15 August the east bound lane of Wallace street at the intersection with Princess Street will be closed and the west bound lane of Wallace Street will be open.

CBD - 14082023.jpg

CBD - 14082023 - 2.jpg

 

 

Macksville CBD Update – Thursday 10 August 2023 4.30pm

The concrete base to Section A will be poured tomorrow morning and it is anticipated that the work will be completed by 10.00am. The asphalt will be laid to Section A on Monday 14 August.

Planning is now underway for Section B and during these works Council will maintain westbound traffic flow through the intersection.

Expected work flow for the next intersection Section B pending favourable weather is:

  • Excavation will commence Tuesday 15 August.
  • The concrete base will be poured Thursday 17 August.
  • The asphalt will be laid Monday 21 August.
  • The Wallace Street intersection will then be open to through traffic on Tuesday 22 August 2023.

Following on from these works either Section C or Section D will commence with the Section chosen to be determined by the availability of a specialised contractor engaged to remove a redundant asbestos water main and install a drainage line.

It is expected that the works to Section’s C and D will take approximately one week each.

Sections E, F and G will not require a concrete sub base and therefore will be completed much faster.

Arrangements will be made regarding the bin service with changes being advised early next week. 

 

MicrosoftTeams-image (90).png

Enquiries: Matthew Leibrandt 0409 829 724 

We apologise for any inconvenience caused and thank you for your patience during this works.

For more information click the link below - 

https://www.nambucca.nsw.gov.au/Business/Engineering-Infrastructure/Projects/Macksville-CBD-Road-Works

 

 

 

Macksville CBD Update – Tuesday 8 August 2023 4.30pm

Asphalt was successfully laid on the second stage of Wallace Street today.

Planning is now underway for the Wallace/Princess Street intersection as Council is committed to maintaining traffic flow through the intersection during the work.

Expected work flow for the next intersection Stage A pending favourable weather is:

  • Excavation will commence Wednesday 9 August.
  • The concrete base will be poured Friday 11 August.
  • The asphalt will be laid Monday 14 August.
  • The lane will be open to through traffic Tuesday 15 August 2023.

08082023_update.png

IMG-1860.jpg

IMG-1862.jpg

 

Update Thursday 3 August 8.30am

The steel reinforcement for the concrete base on the northern side of Wallace Street will be finished today and the concrete will be poured tomorrow, weather permitting. The asphalt pavement is scheduled for Tuesday 8 August to enable the concrete sub-base to set.

The southern side of Wallace Street will be opened to traffic intermittently whenever possible during construction works.  

CBD 3.08.23 3.jpg CBD 3.08.23 2.jpg

Update Monday 31 July 2023 3.30pm

  • Asphalt has been laid today on the southern side of Wallace Street. This layer of asphalt is a heavy duty mix that has a rougher finish. The final wearing course layer will have a smoother finish.
  • Additional geotech test holes will be done tomorrow.
  • Unfortunately the asphalt is not cooling as quickly as anticipated this afternoon so we will be unable to reopen the road tonight.

Update Wednesday 26 July 2023 4.30pm

Council engineers have worked with consultants and contractors to find a pavement solution to solve the unsuitable subgrade issue at the CBD. Council staff and contractors will pour a structural concrete slab to bridge the underlying conditions, this is planned for Friday 28 July 2023 commencing at 5.00am. The asphalt pavement works will be programmed to commence as soon as possible after the concrete has cured.

The original schedule of works has therefore been delayed. A new construction schedule will be developed and communicated to the community in the near future.

 

Update Wednesday 26 July 2023 9.00am

Unfortunately the asphalt works were cancelled again last night due to unforeseen setbacks. We have engaged a consultant  Pavement Engineer who will attend the site to finalise a solution moving forward. Wallace Street will remain closed between the intersection of Princess and Cooper Streets.
We hope to have an updated plan later today and this will be communicated as soon as possible.

 

Update on Macksville CBD Roadworks (25/07/23) - Road Closure

Council wishes to advise that due to the Macksville CBD Upgrade works, Wallace Street has now been closed between the intersection of Princess and Cooper Streets. A road detour has been established to divert all traffic and further details are as follows: 

 

The streets will be closed from 1.00pm Tuesday 25 July 2023 Council will endeavour to have the streets re-opened to traffic as soon as possible.  

Traffic Control: Roadworks signage will be in place while work is being undertaken. 

Enquiries: Matthew Leibrandt 0409 829 724 

We apologise for any inconvenience caused and thank you for your patience during this works.

 

Update on Macksville CBD Roadworks (24/07/23)

Progress to works on the southern side of Wallace Street have been slowed due to an unsuitable subgrade issue.

The total length of the works programmed for today (Monday 24 July) have been reduced and the asphalt night works have been cancelled.

Works will resume on Tuesday on the southern side of Wallace Street with the asphalt works planned for Tuesday evening.

The works schedule as detailed on Council’s website will be delayed by one day.

Council apologises for any inconveniences caused and thanks you for your patience during these works.

 

CBD.jpg

Council wishes to advise that Macksville CBD will have roadworks undertaken in River Street, Princess Street and Wallace Street commencing Monday 24 July with completion scheduled for Tuesday 1 August.
Road detours will be established to divert traffic around the construction site and traffic controllers will be in place. The specific site will change from day to day.