Construction program extended for Way Way Bridge

Published on 20 August 2026

2510 Facebook social tiles_Libraries (14).png

Council wishes to advise works to replace Way Way Bridge on Way Way Creek Road are continuing and the bridge is now scheduled to be completed by about 14 September 2026, weather depending. 

The reason for the delay in program is piling works are taking longer than planned. Council's contractor has hit rock at a shallower depth than expected while piling, which has pushed out the construction program.

For more information about this bridge replacement, contact Council on 6568 2555 or council@nambucca.nsw.gov.au